MRP type PD means the material will be considered by MRP run for planning and trigger the Procurement Proposals after Net reqt calculations.

How do I know my MRP type?

If you want consumption base planning then you have to set an MRP type for the material in the MRP Type field in the material master (View MRP 1) to Reorder point planning, for example VB or VM. But we want to use MRP procedure then we need to maintain PD. or you can check in material master MRP1 view by pressing F4.

What is MRP type ND?

Generally a material is maintained with “ND”, for a material which is not produced continously and most probably based on Customer order. If a material is “ND”, then only MRP is not relevant, but still production and sales may be happening for that material.

What is MRP group?

An MRP group is an object which you can use to assign common control parameters to a group of materials for planning and organizational purposes. You can group materials using MRP Groups. Each of the MRP Group can have its own MRP Parameter set. You can set the MRP group in the material master MRP 1 View.

What is MRP type VB in SAP?

VB falls in the category of consumption based planning..it is manual re order point planning.Mainly used for raw materials and spares B& C type of materials.during MRP run when system checks the stock if it below the re order point then it generates PR for that material.

What is SAP VB?

What is SAP P2?

MRP type P2: With MRP type P2, system will not consider the PIR’s falling within the PTF, planned orders or procurement proposals will be created only. for the requirements which falls outside the PTF. Hence with type P2 there will not be any planned orders created to cover shortages within the PTF.

What is SAP MD61?

MD61 is the demand planning / Planned independent requirement screen. Here you can enter the forcast / demand for the material (normally for the finished goods) You can enter MD61 demand for material wise or create a REquirement number and enter for all materials.

What are MRP controllers?

The MRP controller is responsible for material requirements planning and material availability. They ensure that the materials required to manufacture finished products or superior assemblies are available on time. The MRP controller’s tasks include: Executing and monitoring material requirements planning.